Fall 2024 |
Issue RFP to three finalist vendors
Finalist vendors provide on-site demos for the community |
March-May 2025 |
Final system selection and contract negotiation |
June-December 2025 |
Data preparation for migration |
January-June 2026 |
Migration, staff and community training on the new system |
July 1, 2026 |
New system go-live |